Earthworks and Concrete Works for Cluster 8, 7 and 2 at West Qurna 2 Field

  • Earthworks and Concrete Works for Cluster 8, 7 and 2 at West Qurna 2 Field

Scope of Works

  • excavation
  • supply, install and compaction of back fill materials: sub grade,sub base type
  • electrical and safety work
  • lighting works
  • water and sewer

Contact Number

N/A

Client: ERIELL

Location: West Qurna 2

Value: $1,346,905.76

Completed date: 2016

Category: Civil construction